APPLYING FOR BUILDING PERMIT
Department: City Engineering Office
Location: City Engineer’s Office Compound
1st South Street, Corner Independencia across Activity Center
Section Head: Engr. Teresa Manlangit
Contact No.: 09214038641
Classification: Simple/Complex
Type of Transaction: Government to Government, Government to Business Entity,
Government to Citizen.
ABOUT THE SERVICE:
A building permit is required from an individual or enterprise before any construction, alteration, renovation or conversion can be done on their buildings and structures.
The permit becomes null and void if work does not start within one year from the date of permit. The same thing happens when work is suspended or abandoned at any time after it has started for a period of 120 days.
REQUIREMENT(S):
● Standard Plans duly signed by a Licensed Engineer.
● Permit Forms accomplished and signed by a Licensed Engineer.
● Bill of materials and cost estimates signed by a Civil Engineer.
● Current Real Tax Receipt
● Tax Declaration or TCT of lot (2 Xerox copies)
● If the applicant is not the registered owner of the lot (3 copies each)
1. Duly notarized copy of authorization from lot owner.
2. Duly notarized contract of lease or deed of absolute sale.
● Barangay Construction Clearance (copies)
● Official Receipt
● Zoning Clearance
● Fire Clearance
FEE(S)
● Building permit fee (please refer to the revised and updated IRR of the National Building Code (PD 1096).
Total Processing Time: 1 day and 68 to73 minutes
HOW TO AVAIL OF THE SERVICE:
Step |
Client |
Service Provider |
Time Needed |
Person to approach |
1. |
Go to the public assistance officer -inquire about the service |
-Answer inquiry of the client |
1 minute |
Wilfredo Linganay |
2. |
Proceed to the building permit section:
|
-Conduct briefing/interview to the client -Give the application form and the checklist of requirements. |
5-10 minutes
1 minute |
Virgencita Saquin
Wilfredo Linganay |
3. |
Comply the requirements provided in the checklist |
|
|
|
4. |
Go back to the building permit section: -submit duly accomplished application form and the requirements to the employee in-charge for review. |
-Receive and review duly accomplished form and documents submitted |
5 minutes |
Virgencita Saquin |
5. |
Wait for the:
|
-Give the schedule of site inspection as to line and grade requirements -Compute permit fees and fire inspection fee.
|
10 minutes
30 minutes |
Teresa Manlangit
|
6. |
|
Advise client to:
|
1 minute 1 minute |
Teresa Manlangit
|
7. |
Go back to the building permit section. -Present the official receipt, clearance and documents. |
-Receive and review/record
-Official receipt, clearance and documents. |
5 minutes |
Virgencita Saquin
Wilfredo Linganay
|
8. |
Wait while:
|
-Process the building permit. -Approve the building permit. |
1 day
5 minutes |
Geronimo Mantuhac Rene Linganay Celso Collantes Teresa Manlangit Leah Saturinas |
9. |
Return to the building permit section -get the building permit
-sign the releasing logbook. |
-Release permit.
-Request client to sign in the logbook. |
3 minutes
1 minute |
Teresa Manlangit
Wilfredo Linganay |
FEEDBACK AND COMPLAINTS MECHANISM |
|
How to send feedback? |
Clients may visit personally or text/call the City Engineer’s Office/Building Permit Section |
How feedbacks are processed? |
The employee concerned or the Building Official will be immediately informed of any complaints thru text or call. |
How to file complaint? |
A complaint letter maybe filed addressed to the Building Official stating the complaints whether it be on an employee or any matter related to the work being complained about. |
How complaints are processed? |
Inform the employee concerned, get the employee’s side of the story and make a written answer to the complainant. |
Contact Information of CCB, PCC, ARTA |
|