ABOUT THE SERVICE:
An occupancy permit is to be secured by a property owner before any building or structure can be used or occupied. The same holds true if there is any change in the present usage or occupancy classification of a structure or any portion thereof. The permit is usually secured when construction is completed.
REQUIREMENT(S):
● Certificate of completion from the building official
● Certificate of completion – mechanical, electrical, sanitary, plumbing permits
● Certificate of final electrical inspection report by the Bureau of Fire Protection
FEE(S)
● Please refer to the revised and updated Implementing Rules and Regulations of the National Building Code (PD 1096)
Total Processing Time: 1 day and 14 minutes
HOW TO AVAIL OF THE SERVICE:
Step |
Client |
Service Provider |
Time Needed |
Person to approach |
1. |
Inquire about the service from the public assistance officer |
-Answer inquiry of the client |
1 minute |
Wilfredo Linganay
|
2. |
Proceed to the building permit section: -For the briefing -Secure completion form and requirements from the staff in charge. |
-Conduct client briefing on the requirements
-Give completion form and requirements to the client.
|
1 minute |
Virgencita Saquin
|
3. |
Comply the requirements.
|
|
|
|
4. |
Return to the building permit section: -submit duly accomplished form and the requirements. |
-Receive and review the duly accomplished form and the requirements. |
2 minutes |
Teresa Manlangit |
5. |
Wait while:
|
-Prepare, process certificate of occupancy. -Advise client to go to the City Planning Office and the Fire Department.
-Conduct final inspection of building.
-Approve/sign certificate of occupancy. |
1 minute
2 minutes
1 day
5 minutes
|
Wilfredo Linganay Virgencita Saquin Geronimo Mantuhac Rene Linganay Teresa Manlangit Celso Collantes Leah Saturinas
|
6. |
Go back to the building permit section -get the original copy of the occupancy permit. -sign the releasing logbook. |
-Give the client’s copy of the occupancy permit. -Request client to sign the logbook. |
1 minute
1 minute |
Virgencita Saquin
Wilfredo Linganay |
FEEDBACK AND COMPLAINTS MECHANISM |
|
How to send feedback? |
Clients may visit personally or text/call the City Engineer’s Office/Building Permit Section |
How feedbacks are processed? |
The employee concerned or the Building Official will be immediately informed of any complaints thru text or call. |
How to file complaint? |
A complaint letter maybe filed addressed to the Building Official stating the complaints whether it be on an employee or any matter related to the work being complained about. |
How complaints are processed? |
Inform the employee concerned, get the employee’s side of the story and make a written answer to the complainant. |