Pre-Audit of Disbursement Vouchers – Infrastructure Projects
The Pre-Audit Division provides a thorough review of the supporting documents and all its attachments before it will be processed for payment to contractors and suppliers.
Office or Division: Pre-Audit Division
Classification: Highly Technical
Type of Transaction: G2B - Government to Business
Who May Avail: All
CHECKLIST OF REQUIREMENTS
Advance Payment /15% Mobilization
- Disbursement Voucher from the Requesting Office
- Obligation Request City from the Budget Office
- Certification of Availability of Funds City from the Budget Office
- Letter request from contractors for advance payment / 15% mobilization (duly received by CMO) from the Contractor
- Irrevocable Standby Letter of Credit / Security Bond / Bank Guarantee from the Contractor
- Approved Purchase Request from the Requesting Office
- Approved PPMP / APP from the Requesting Office
- Sanggunian Panglungsod Ordinance from the City Council Office
- Transmittal letter to COA for review from the Requesting Office
- Bidding Documents from the BAC Secretariat
Progress Payments
- Disbursement Voucher from the Requesting Office
- Photocopy of original Obligation Request updated based on the status of the contract being processed from the City Budget Office
- Letter request from contractors for progress billing (duly received by CMO) from the Contractor
- Transmittal letter to COA for review from the Requesting Office
- Statement of Work Accomplished (SWA) / Progress Billing from the Contractor
- Inspection Report by the Agency‘s Authorized Engineer from the City Engineer‘s Office
- Results of Test Analysis, if applicable from the Contractor
- Statement of Time Elapsed from the Contractor
- Monthly Certificate of Payment from the Contractor
- Billing Summary from the Contractor
- Executive Summary from the Contractor
- Background Information from the Contractor
- Certificate of Compliance from the Contractor
- Contractor‘s Affidavit on payment of laborers and materials from the Contractor
- Pictures, before, during and after construction of items of work especially the embedded items from the Contractor
- Approved Extension, Suspension and Resumption (if applicable) from the City Engineer‘s Office
- Certification of No Pending Obligation of Labor and Materials to be signed by the contractor, Project Engineer and Foreman from the Contractor
- Approved Variation Order if there are changes in the contract from the City Engineer‘s Office
- Agency Approved Program of Work and Detailed Estimates from the City Engineer‘s Office
- Photocopy of vouchers of all previous payments from the City Engineer‘s Office
Prescribed documents prior to Contract Signing
- Construction Schedule and S-Curve from the Contractor
- Manpower Schedule from the Contractor
- Construction Method from the Contractor
- Equipment Utilization Schedule from the Contractor
- Construction Safety and Health Program from theContractor
- PERT/CPM of winning bid for Infrastructure as prepared by contractor from the Contractor
- Affidavit of Site Inspection from the Contractor
Final Billing
- Disbursement Voucher from the Requesting Office
- Photocopy of original Obligation Request updated based on the status of the contract being processed City from the Budget Office
- Letter request from contractors for final billing (duly received by CMO) from the Contractor
- Transmittal letter to COA for review from the Requesting Office
- Statement of Work Accomplished (SWA) from the Contractor
- Inspection Report by the Agency‘s Authorized Engineer City from the Engineer‘s Office
- Results of Test Analysis, if applicable from the Contractor
- Statement of Time Elapsed from the Contractor
- Monthly Certificate of Payment from the Contractor
- Billing Summary from the Contractor
- Executive Summary from the Contractor
- Background Information from the Contractor
- Certificate of Compliance from the Contractor
- Contractor‘s Affidavit on payment of laborers and materials from the Contractor
- Pictures, before, during and after construction of items of work especially the embedded items from the Contractor
- Certification of No Pending Obligation of Labor and Materials to be signed by the contractor, Project Engineer and Foreman from the Contractor
- Warranty Security (irrevocable standby letter of credit from the bank 10% of Contract Price) or Surety Bond 30% of Contract Price (if insurance) from the Contractor
- COA Technical Evaluation Report for Infrastructure Project from COA Regional Office – CDO from the COA Regional Office
- Certificate of Project Completion from the City Engineer‘s Office
- Certificate of Acceptance from the City Engineer‘s Office
- Completion Report and Acknowledgement of Turn Over and Custody of Completed Project from the City Engineer‘s Office
- Photocopy of vouchers of all previous payments from the City Engineer‘s Office
Release of Retention Money
- Disbursement Voucher from the Requesting Office
- Photocopy of original Obligation Request updated based on the status of the contract being processed from the City Budget Office
- Contractors Request for Substitution duly received by CMO from the Contractor
- Irrevocable Standby Letter of Credit from the Contractor
- Copy of the Contract of Agreement from the BAC Secretariat
- Copy of Notice to Proceed from the BAC Secretariat
- Copy of Notice of Award from the BAC Secretariat
- Copy of paid voucher of all billing showing the deduction of retention from the City Engineer‘s Office
- Certificate of Turnover from the City Engineer‘s Office
- Certificate of Acceptance from the City Engineer‘s Office
- Certificate of Project Completion from the City Engineer‘s Office
- COA Technical Evaluation Report for Infrastructure Project from COA Regional Office – CDO from the COA Regional Office
NOTE: Submit two sets of disbursement voucher with complete supporting documents: 1st Set Original Copy; 2nd Set Photocopy
Steps | Service Details |
---|---|
1 | Client Steps: The processor submits the completed documents to the PreAudit Division (Table 1) for assessment and verification. Agency Action: Records the documents received in the logbook and check the supporting documents for completeness. (If complete, stamps “Received” and indicates date of receipt and initials on the stamped "Received" portion. Any incomplete documents will be return to the party concerned.) Fees to be Paid: None Processing Time: 3 Hours (from receipt) Person Responsible: Management Audit Analyst II Office of the City Accountant (OCA) |
2 | Agency Action: Conducts pre-audit of the transaction by checking the accuracy, propriety and validity of the documents. Fees to be Paid: None Processing Time: 8 Days Person Responsible: Management Audit Analyst II Office of the City Accountant (OCA) |
Agency Action: For existing claimant, retrieves Index of Payments (IoP) and determines if claim is in order. For first-time claimant, prepared IoP. Fees to be Paid: None Processing Time: 30 Minutes Person Responsible: Management Audit Analyst II Office of the City |
|
Agency Action: If prior payments already made Accountant (OCA) on the same claim, return the documents and inform the requesting office/party of prior payment made. | |
Agency Action: If in order, verifies Obligation Request Slip against Disbursement Voucher (DV). If the amounts are the same, record the details in the IoP. If the amounts differ, documents will be forwarded back to the Budget Office for update of amounts. | |
Agency Action: Forwards the verified documents to City Accountant. Fees to be Paid: None Processing Time: 5 Minutes Person Responsible: Management Audit Analyst II Office of the City Accountant (OCA) |
|
Agency Action: Reviews and approves the DV. Fees to be Paid: None Processing Time: 5 Hours Person Responsible: City Accountant I Office of the City Accountant (OCA) |
|
Agency Action: Records in the Logbook the release of the complete documents to the processor for approval and signature of the City Mayor or her Authorized Representative. Fees to be Paid: None Processing Time: 10 Minutes Person Responsible: Management Audit Analyst II Office of the City Accountant (OCA) |
Total Fees to be Paid: None
Total Processing Time: 9 Days, 45 Minutes