Issuance of Occupancy Permit
n occupancy permit is to be secured by a property owner before any building or structure can be used or occupied. The same holds true if there is any change in the present usage or occupancy classification of a structure or any portion thereof. The permit is usually secured when construction is completed.
Office or Division: City Engineer’s Office (Office of the Building Official)
Classification: Simple
Type of Transaction: G2G - Government to Government; G2B - Government to Business; G2C - Government to Citizen
Who May Avail: Client(s) who is/are securing its occupancy permit.
CHECKLIST OF REQUIREMENTS
- Certificate of Completion Form Signed by the Supervising Architect, Civil Engineer during construction (5 Original Copies) from the Building Permit In-charge, City Engineer’s Office, Tangub City
- Duly Signed Certificate of Completion – Mechanical, Electrical, Sanitary, Plumbing Permits (3 Copies) from the Building Permit In-charge, City Engineer’s Office, Tangub City
- Duly Signed Certificate of Final Electrical Inspection Report (5 Copies) from the Bureau of Fire and Protection Office, 1st Street, Tangub City
- Official Receipt from the City Treasurer’s Office Ground Floor of City Hall, Tangub City
WHERE TO SECURE
Land area to be planted
Steps | Service Details | ||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Client Steps: Go to City Engineer’s Office (Office of the Building Official). Agency Action: Request the client to sign in the logbook. Fees to be Paid: None Processing Time: 1 Minute Person Responsible: Engineer II from the City Engineer’s Office |
||||||||||||||||||||||||||||||||||||
1.2 | Client Steps: Sign in the logbook. | ||||||||||||||||||||||||||||||||||||
2 | Client Steps: Proceed to the Building Permit Section In-Charge. Agency Action: Conduct client briefing on the requirement Fees to be Paid: None Processing Time: 1 Minute Person Responsible: Engineer II from the City Engineer’s Office |
||||||||||||||||||||||||||||||||||||
2.1 | Client Steps: For the briefing Agency Action: Give completion form and checklist of requirements to the client. Fees to be Paid: None Processing Time: 1 Minute Person Responsible: Engineer II from the City Engineer’s Office |
||||||||||||||||||||||||||||||||||||
2.2 | Client Steps: Secure completion form and checklist of requirements. Agency Action: Provide the client the computation of fees. Fees to be Paid: None Processing Time: 20 Minutes Person Responsible: Engineer II from the City Engineer’s Office |
||||||||||||||||||||||||||||||||||||
2.3 | Client Steps: Secure computation of occupancy permit. Agency Action: Advice the client to proceed to the City Treasurer’s Office. Fees to be Paid: None Processing Time: 1 Minute Person Responsible: Engineer II from the City Engineer’s Office |
||||||||||||||||||||||||||||||||||||
Client Steps: Proceed to City Treasurer’s Office to pay the computed amount for occupancy permit. Residential
Commercial
Institutional
|
|||||||||||||||||||||||||||||||||||||
4 | Client Steps: Comply the requirements for occupancy permit. | ||||||||||||||||||||||||||||||||||||
5 | Client Steps: Return to the Building Permit Section. Agency Action: Receive, record and return to the client the official receipt, clearances and other documents. Fees to be Paid: None Processing Time: 2 Minutes Person Responsible: Engineer II from the City Engineer’s Office |
||||||||||||||||||||||||||||||||||||
5.1 | Client Steps: Present the official receipt, clearance and other documents. | ||||||||||||||||||||||||||||||||||||
6 | Client Steps: Wait while the Certificate of Occupancy Permit is processed. Agency Action: Prepare, process Certificate of Occupancy.; Advise client to go to the Bureau Fire and Protection to secure Fire Safety Inspection Certificate. Fees to be Paid: None Processing Time: 2 Minutes Person Responsible: Engineer II from the City Engineer’s Office |
||||||||||||||||||||||||||||||||||||
7 | Client Steps: Proceed to Bureau of Fire and Protection to secure Fire Safety Inspection Certificate. Agency Action: None Fees to be Paid: None Processing Time: 1 Day Person Responsible: Bureau of Fire and Protection Chief |
||||||||||||||||||||||||||||||||||||
8 |
Client Steps: Return to Building Permit Section In-Charge.
|
||||||||||||||||||||||||||||||||||||
8.1 |
Client Steps: The Certificate of Occupancy Permit is processed.
|
||||||||||||||||||||||||||||||||||||
8.2 | Agency Action: The Building Official approved the Occupancy Permit. Fees to be Paid: None Processing Time: 5 Minutes Person Responsible: City Engineer (Building Official) from the City Engineer’s Office |
||||||||||||||||||||||||||||||||||||
9 | Client Steps: Return to Building Permit In-Charge. Agency Action: Release the approved Occupancy Permit to the client. Fees to be Paid: None Processing Time: 3 Minutes Person Responsible: Engineer II from the City Engineer’s Office |
||||||||||||||||||||||||||||||||||||
9.1 | Client Steps: Get the original copy of the Occupancy Permit. | ||||||||||||||||||||||||||||||||||||
9.2 | Client Steps: Sign the releasing logbook. Agency Action: Request the client to sign the releasing logbook. Fees to be Paid: None Processing Time: 1 Minute Person Responsible: Engineer II from the City Engineer’s Office |
Total Fees to be Paid: None
Total Processing Time: 2 Days, 56 Minutes